Wednesday, April 15, 2009

April 15

Christ is risen! It has been busy here at the old building with holy week and went and Easter. It has also been a busy time over at the new building.

Crews have finished the exterior siding!

The water fountains have been installed.
On April 6, I got a shot of the women's bathroom counter.
This morning the fellows from Northern Electric were installing exterior lights.
The area that is marked off by the red chalk line designates the concrete that will be poured shortly. (And no, that is not a cowboy hat I am wearing; it is a fedora.)
The second door inside the main door has been hung, and the windows are being framed.
Office and classroom doors are up!
Exit signs as well.
A peak in the men's bathroom today shows that the porcelain and steel are all in. And yes, we put a baby changing table in the men's room, too.

No comments: