Sunday, November 30, 2008

November 26

Here is the work that was accomplished the three days before Thanksgiving.West wing sheeted
South wall of worship space framed.
Looking from the worship area west into the offices & sunday school rooms.
Looking east; kitchen on the left, classrooms on the right
Next time you see these trusses, they should be up in the air!

November 24

Exterior walls in the Education / Office wing are up, and framing is underway on the interior walls.
Below, the view from the NE corner of the lot.

Saturday, November 22, 2008

The Big Picture
North wall of the sanctuary.

The basement entrance
Looking from the kitchen door (NW corner) toward the sanctuary and the road ...

At the end of work on Thursday (they do not work Fridays), the crew had exterior walls framed all the way around the bathrooms, kitchen, classrooms and offices. The North wall of the sanctuary is under construction and the south wall is framed and ready to raise!

November 21

November 20

Nov 19

In the 6 weeks that followed the groundbreaking, Joe got the plumbing and heating ducts in place, the slab got poured, and then we waited for approval on a couple of truss elements. And waited. And waited.

Finally, on November 19, framing began!

October 5 Groundbreaking




Before October 5 III





Before October 5 II





Before October 5






Here are the pictures of the work that got done before the October 5 "Groundbreaking"

Wednesday, November 19, 2008

Welcome

This is a blog to show the progress of the building of a new facility at Grace Lutheran Church in Hayward, Wisconsin.