Blog entries will probably slow down a little now, as there is less obvious work going on. Today, we caught the following:
Windows are in, as seen from NE corner of lot.
Roofers still have some work to do as from the SE corner.
Windows in the Worship space.
View from the Pastor's office.
I told you the electricians had been busy ....
Hope everyone had a blessed Christmas.
Friday, December 26, 2008
Monday, December 22, 2008
December 22
Saturday, December 20, 2008
December 20
Friday, December 19, 2008
Deember 19
Thursday, December 18, 2008
December 18
Wednesday, December 17, 2008
December 17
I understand that the contractor's boss called the crew off the job on Tuesday due to weather. So today they were hard at work on the roof of the worship space.And the east wall of the worship space is going in.
And here is a longer view.
If you want a better view than any of these pictures, click on the picture and it will get bigger in your web browser.
And here is a longer view.
If you want a better view than any of these pictures, click on the picture and it will get bigger in your web browser.
Tuesday, December 16, 2008
December 16
Thursday, December 11, 2008
December 11
December 10
Gary & Karen Gustafson made up some lasagna for the crew, which this day included framers, electricians, roofers and others. (That is Scott Jorgenson who is doing the roofing, leaning on the furnace below, chatting with Gary and Joe Kreyer, doing the heat & plumbing.)
These two framers, below, had already eaten and were taking a little quiet time in the car.
As you can see, the north wall of the worship space is rising into the air.
These two framers, below, had already eaten and were taking a little quiet time in the car.
As you can see, the north wall of the worship space is rising into the air.
Tuesday, December 9, 2008
Up on the Rooftop, roofer's paws!
Friday Dec 5
They did some work on Monday as well, but it was mostly small, inside stuff, and I do not go inside when the guys with the tools and hardhats are working.
Up in the attic.
In the kitchen looking SE.
4. In the hallway, kitchen on the left, classrooms & offices on right, looking east into the Worship space.
The Double classroom (a portable divider wall will be installed.)
The warmest part of the building, as of now: the basement.
Thursday, December 4, 2008
Aerial Shots of the site
Subscribe to: